Preparatory civil works are now almost complete, and construction of the concrete plinth for the SSE switchgear has been carried out; the access track is ready save for reinforcement over two culverts. SSE have not yet begun construction of the grid connection cable and await formal sign-off of the wayleave form Laggan Estates, which we understand is imminent. Delivery of the transformer substation remains on schedule and the customer’s preliminary works for the electrical in
stallation are complete. The overall project schedule still looks comfortable,